§ La. R.S. 18:1367.4(untitled)

en · 2,175 chars · active
Authority to resolve contract and breach of contract controversies other than professional,
personal, consulting, and social services contracts
A. Applicability. This Section applies to controversies between the state and a contractor and which
arise under or by virtue of a contract between them. This includes without limitation controversies based
upon breach of contract, mistake, misrepresentation, or other cause for contract modification or rescission.
Any contractor who seeks a remedy with regard to such controversy shall file a complaint with the chief
procurement officer.
B. Authority. The chief procurement officer or his designee is authorized, prior to the
commencement of an action in court concerning the controversy, to settle and resolve, with the approval of
the attorney general, a controversy described in Subsection A of this Section. This authority shall be
exercised in accordance with regulations.
C. Decision. If such a claim or controversy is not resolved by mutual agreement, the chief
procurement officer or his designee shall promptly issue a decision in writing. The decision shall do all of
the following:
(1) State the reasons for the action taken.
(2) Inform the contractor of its right to administrative and judicial review as provided in this
Subpart.
D. Notice of decision. A copy of the decision under Subsection C of this Section shall be mailed
or otherwise furnished immediately to the contractor.
House of Representatives Database
Louisiana Election Code – 269
R.S. 18:1367.7
E. Finality of decision. The decision under Subsection C of this Section shall be final and
conclusive unless one of the following applies:
(1) The decision is fraudulent.
(2) The contractor has timely appealed administratively to the commissioner in accordance with R.S.
18:1367.8.
F. Failure to render timely decision. If the chief procurement officer or his designee does not issue
the written decision required under Subsection C of this Section within sixty days after written request for
a final decision, or within such longer period as may be agreed upon by the parties, then the contractor may
proceed as if an adverse decision had been received.